9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be
78
81
55
30
The correct Answer is:B
Step by step video & text solution for 9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be by Maths experts to help you in doubts & scoring excellent marks in Class 12 exams.
Updated on:21/07/2023Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT PUBLICATION BIHARCHAPTER - TIME AND WORKEXERCISE - Exam Booster for Cracking Exam
18 Videos
- TIME AND DISTANCEBOOK - ARIHANT PUBLICATION BIHARCHAPTER - TIME AND DISTANCEEXERCISE - Exam Booster for Cracking Exam
25 Videos
- TRIGONOMETRIC IDENTITIESBOOK - ARIHANT PUBLICATION BIHARCHAPTER - TRIGONOMETRIC IDENTITIESEXERCISE - EXAM BOOSTER (FOR CRACKING EXAM)
35 Videos
Similar Questions
A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
View SolutionKiran covers a certain distance 80 km/h and returns back to the same point at 20 km/h. Then, the average speed during the whole journey be
View Solutioncot85∘+cos75∘ can be expressed as
View Solution4 पुरुष तथा 6 महिलाएँ किसी काम को 8 दिनों में समाप्त करते है और 2 पुरुष तथा 9 महिलाएँ भी काम को 8 दिनों में समाप्त करेगी ?
View Solutionकुछ पुरुष एक काम को 30 दिनों में ख़त्म कर सकते है यदि 5 पुरुष और आ जाएं तो काम 10 दिन पहले ख़त्म हो जाता है आरभ में कितने पुरुष थे ?
View Solution8 पुरुष 9 घंटे प्रतिदिन काम करके एक काम को 20 दिनों में ख़त्म करते है , तो 7 पुरुष 10 घंटे प्रतिदिन काम करके कितने दिनों में काम ख़त्म करेंगे ?
View SolutionIf 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View SolutionIf 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .
View Solution16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution5 men can do a work in 10 days. How many men will be required to finish the work in 5 days?
View Solution16 men finished one-third work in 6 days. The number of additional men are required to complete the remaining job in next 6 days:
View Solution70 men have to finish a work in 60 days. In 45 days only 40% of the work was completed. How many additional men will be required to finish the remaining work in time?
View Solution120 men working 10 hours a day can finish a piece of work in 85 days. After 10 days all the men went on strike and the work was stopped for 25 days. In order to finish the work on time, additional men should be employed so that they can finish the work on time by working 8 hours a day?
View Solution60 men can finish a work in 50 days. If 20 men join the work every 10 days, then in how many days will the work be finished?
View Solution