If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?

A

10

B

20

C

30

D

40

Video Solution
Text Solution
Verified by Experts

The correct Answer is:C


Let the required number of men be x.
We have, M1D1H1W1=M2D2H2W2
(20)(15)(10)1=(20+x)(10)(12)2
20+x=50x=30.

|


Similar Questions


Knowledge Check

  • If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • 7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?

    A28
    B21
    C14
    D7