10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
12 days
10 days
8 days
4 days
The correct Answer is:B
To solve the problem step by step, we will first determine the total work done in terms of "man-days" and then find out how many days it will take for 4 men and 6 women to complete that work.
Step 1: Determine the total work done by 10 men and 8 women in 5 days.
Let the work done by one man in one day be M and the work done by one woman in one day be W.
According to the problem, we know that:
- W=12M (i.e., one woman does half the work of one man)
Now, the total work done by 10 men and 8 women in one day is:
Work done in one day=10M+8W
Substituting W:
=10M+8(12M)=10M+4M=14M
Since they complete the work in 5 days, the total work Wtotal is:
Wtotal=Work done in one day×Number of days=14M×5=70M
Step 2: Determine the work done by 4 men and 6 women in one day.
Now, we need to find out how much work 4 men and 6 women can do in one day:
Work done in one day by 4 men and 6 women=4M+6W
Substituting W:
=4M+6(12M)=4M+3M=7M
Step 3: Calculate the number of days required for 4 men and 6 women to complete the total work.
Now, we need to find the number of days D it will take for 4 men and 6 women to complete the total work of 70M:
Total work=Work done in one day×Number of days
70M=7M×D
Dividing both sides by 7M:
D=70M7M=10
Conclusion
Thus, it will take 4 men and 6 women 10 days to complete the work.
---
- W=12M (i.e., one woman does half the work of one man)
Work done in one day=10M+8W
Substituting W:
=10M+8(12M)=10M+4M=14M
Wtotal=Work done in one day×Number of days=14M×5=70M
Work done in one day by 4 men and 6 women=4M+6W
Substituting W:
=4M+6(12M)=4M+3M=7M
Total work=Work done in one day×Number of days
70M=7M×D
Dividing both sides by 7M:
D=70M7M=10
Similar Questions
If 3 men and 7 women can complete a work in 10 days and 4 men and 6 women need 8 days to complete the same work. In how many days will 10 women complete the same work?
View Solution8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution8 men and 14 women are working together in a field. After working for 3 days, 5 men and 8 women leave the work. How many more days will be required to complete the work?
I. 19 men and 12 women together can complete the work in 18 days.
II. 16 men complete two-third of the work in 16 days
III. In a day, the work done by three men is equal to the work done by four women.
View SolutionIn how manu days can the work be done by 9 men and 15 women ?
(i) 6 men and 5 women can complete the cork in 6 days.
(ii) 3 men and 4 women can complete the work in 10 days
(iii) 18 men and 15 women can complete the work in 2 days.
View Solution7 men and 3 women complete the work together in 10 days. 8 men and 2 women complete the same work in 8 days. How much work can be done by 12 men in one day?
View Solution24 men can do work in X days and 32 women can do the same work in (X+8) days. The ratio of work done by 15 men and 12 women in the same time is 3 : 1 . In how many days, the work will be completed if 5 men and 4 women work together ?
View Solution20 men can finish a work in 10 days, while 12 women can finish it in 10 days. If 15 men and 6 women can complete that work. Find in how many days it will take to complete the work?
View Solution