A can do a job in 15 days, B in 10 days and C in 30 days. If A is helped by B and C on every third day, then the job will be completed in
613 days
813 days
8 days
9 days
The correct Answer is:D
To solve the problem step by step, we will calculate the work done by A, B, and C, and how they contribute to completing the job over a period of days.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the job in 15 days, so in one day, A does:
Work done by A in one day=115 of the job=2 units
- B can complete the job in 10 days, so in one day, B does:
Work done by B in one day=110 of the job=3 units
- C can complete the job in 30 days, so in one day, C does:
Work done by C in one day=130 of the job=1 unit
Step 2: Calculate the total work done in a cycle of 3 days.
- Day 1: A works alone:
Total work done on Day 1=2 units
- Day 2: A works alone:
Total work done on Day 2=2 units
- Day 3: A, B, and C work together:
Total work done on Day 3=2+3+1=6 units
Step 3: Calculate the total work done in 3 days.
- Total work done in 3 days:
Total work in 3 days=2+2+6=10 units
Step 4: Determine how many cycles are needed to complete the job.
- The total work required is 30 units. Since 10 units are completed in 3 days, we can find out how many cycles are needed:
Number of cycles=30 units10 units/cycle=3 cycles
Step 5: Calculate the total time taken to complete the job.
- Since each cycle takes 3 days, the total time taken to complete 3 cycles is:
Total time=3 cycles×3 days/cycle=9 days
Conclusion:
The job will be completed in 9 days.
---
Work done by A in one day=115 of the job=2 units
Work done by B in one day=110 of the job=3 units
Work done by C in one day=130 of the job=1 unit
Total work done on Day 1=2 units
Total work done on Day 2=2 units
Total work done on Day 3=2+3+1=6 units
Total work in 3 days=2+2+6=10 units
Number of cycles=30 units10 units/cycle=3 cycles
Total time=3 cycles×3 days/cycle=9 days
Similar Questions
Knowledge Check
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
A5 daysB756 daysC10 daysD1523 daysA and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :
A5 daysB756 daysC10 daysD1523 daysA and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :
A5 daysB756 daysC10 daysD1523days
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionA and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
View SolutionA man completes a job in 15 days. His son completes the same job in 10 days. If both work together then in how many days the work will be completed ?
View Solution
