A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
Step by step video & image solution for A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
An unbiased die is thrown. What is the probability of getting:
(i) an even number
(ii) a multiple of 3
(iii) an even number or a multiple of 3
(iv) an even number and a multiple of 3
(v) a number 3 or 4
(vi) an odd number
(vii) a number less than 5
(viii) a number greater than 3
(ix) a number between 3 and 6
View Solutiondetermine whether following are polynomial or not 2x23−3x22+x−5 (2)x32−3x2+5x12+x−1
View SolutionA work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
View SolutionA work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
View Solution7 men can complete a work in 52 days. In how many days will 13 men finish the same work.
View SolutionIf 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?
View Solution8 men can finish a piece of work in 15 hours.In how many hours can 20 men finish it?
View SolutionA work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
View SolutionA contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
View SolutionA contractor employs 36 men on a job and they do 1/2 of the work in 16 days. He employs 12 additional men to complete the remainder of the work. In how many days will the remaining work be finished?
View SolutionIf 45 men can finish a piece of work in 12 days, in how many days will 30 men finish the same work?
View SolutionA contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View Solution4 men and 5 women can complete a piece of work in 15 days while 9 men and 6 women can complete the same work in 10 days. How many women along with 4 men must be employed to complete the same work in 7 days?
View Solution8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution