A does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?
The correct Answer is:1313 day
To solve the problem step by step, let's break down the information given and find the total time taken for A, B, and C to complete the work together.
Step 1: Define the work done by A, B, and C
- Let the work done by B in one day be x.
- Since A does half as much work as B, the work done by A in one day is x2.
- C does half as much work as A and B together. The work done by A and B together is x2+x=3x2. Therefore, the work done by C in one day is 12×3x2=3x4.
Step 2: Determine C's total work
- We know that C alone can finish the work in 40 days. This means the total work can be calculated as:
Total Work=C's work per day×Number of days
Total Work=3x4×40=30x
Step 3: Calculate the total work done by A, B, and C together
- Now, we will find the total work done by A, B, and C in one day.
- The total work done by A, B, and C together is:
Total Work per day=A+B+C=x2+x+3x4
- To add these, we need a common denominator. The common denominator for 2, 1, and 4 is 4.
=2x4+4x4+3x4=2x+4x+3x4=9x4
Step 4: Calculate the time taken for A, B, and C to finish the work together
- We know the total work is 30x and the work done together in one day is 9x4.
- The time taken to complete the work together is:
Time=Total WorkTotal Work per day=30x9x4=30x×49x=1209=403 days
Final Answer
Thus, A, B, and C together will finish the work in 403 days, which is approximately 13.33 days.
- Let the work done by B in one day be x.
- Since A does half as much work as B, the work done by A in one day is x2.
- C does half as much work as A and B together. The work done by A and B together is x2+x=3x2. Therefore, the work done by C in one day is 12×3x2=3x4.
- We know that C alone can finish the work in 40 days. This means the total work can be calculated as:
Total Work=C's work per day×Number of days
Total Work=3x4×40=30x
- Now, we will find the total work done by A, B, and C in one day.
- The total work done by A, B, and C together is:
Total Work per day=A+B+C=x2+x+3x4
- To add these, we need a common denominator. The common denominator for 2, 1, and 4 is 4.
=2x4+4x4+3x4=2x+4x+3x4=9x4
- We know the total work is 30x and the work done together in one day is 9x4.
- The time taken to complete the work together is:
Time=Total WorkTotal Work per day=30x9x4=30x×49x=1209=403 days
Thus, A, B, and C together will finish the work in 403 days, which is approximately 13.33 days.
Topper's Solved these Questions
Similar Questions
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
A is 50% as efficient as B. C does half of the work done by A and B together. If C alone does the work in 20 days, then A, B and C together can do the work in
A523 daysB623 daysC6 daysD7 daysA does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?
A523 daysB623 daysC6 daysD7 daysA can do one and a half as much of a work which B can do in one day. B alone can do a piece of work in 18 days. They together can finish that work in
A1015 daysB1115 daysC515 daysD715 days
A can finish 80% of work done by B in 20% more time taken by B. Working together they can finish the work in 40 days. In how many days they will finish the work working alone?
View SolutionA and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
View SolutionA can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
View SolutionA is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
View Solution