A man do a work in 12 days working 8 h per day. If he does 6 h per day, what would be the number of days taken by him?
12 days
14 days
16 days
18 days
The correct Answer is:C
To solve the problem step by step, we can follow these instructions:
Step 1: Calculate the total work done
The man works for 12 days, and each day he works for 8 hours.
To find the total work done, we multiply the number of days by the number of hours worked each day.
Total Work=Number of Days×Hours per Day=12days×8hours/day=96hours
Step 2: Determine the number of days required at 6 hours per day
Now that we know the total work is 96 hours, we need to find out how many days it will take if he works 6 hours each day.
We can use the formula:
Number of Days=Total WorkHours per Day
Substituting the values we have:
Number of Days=96hours6hours/day=16days
Conclusion
Thus, if the man works for 6 hours per day, it will take him 16 days to complete the work.
---
The man works for 12 days, and each day he works for 8 hours.
To find the total work done, we multiply the number of days by the number of hours worked each day.
Now that we know the total work is 96 hours, we need to find out how many days it will take if he works 6 hours each day.
Thus, if the man works for 6 hours per day, it will take him 16 days to complete the work.
Similar Questions
2 men each working 5 hour per day can finish a job in 12 days. How long will 4 men each working 2 hours per day take to finish the same job?
View SolutionBy working 8 hours a day. A can complete a work in 10 day. If the reduces the work hours by 3 hours per day, them he can complete the same work in ……………….. Days.
View SolutionA certain number of men can do a work in 15 days working 8 hours a days.If the number of men is decreased 13, then in how many days can twice the previous work be completed by the remaining men working 5 hours per day?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?
View SolutionIf 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
View Solution50 persons can do a work in 12 days, working 6 h per day. 60 persons can do the same work in 8 days, working x h per days.The value of x is
View Solution