If A can complete a project in 3 days, B can complete the same project in 4 days while C can complete it in 5 days. All of them stated the project together but after 3 days C left, after 4 days B left and after 5 days A left, then how many projects they have finished in 5 days?
2
1
3
4
The correct Answer is:C
To solve the problem step by step, we first need to determine the work done by each person (A, B, and C) in a day and then calculate how much work they complete together over the specified time.
Step 1: Determine the work rate of A, B, and C
- A can complete the project in 3 days, so A's work rate is:
Work rate of A=1 project3 days=13 projects per day
- B can complete the project in 4 days, so B's work rate is:
Work rate of B=1 project4 days=14 projects per day
- C can complete the project in 5 days, so C's work rate is:
Work rate of C=1 project5 days=15 projects per day
Step 2: Find the combined work rate of A, B, and C
To find the total work rate when all three work together, we add their individual work rates:
Combined work rate=13+14+15
To add these fractions, we need a common denominator. The least common multiple (LCM) of 3, 4, and 5 is 60. Thus, we convert each fraction:
13=2060,14=1560,15=1260
Now we can add them:
Combined work rate=2060+1560+1260=4760 projects per day
Step 3: Calculate the work done in the first 3 days
In the first 3 days, all three work together:
Work done in 3 days=3×4760=14160 projects
Step 4: Calculate the work done by B and A after C leaves
After 3 days, C leaves. Now A and B continue working together for the next day (Day 4):
Work done by A and B in 1 day=13+14=2060+1560=3560 projects
So, after Day 4, the total work done is:
Total work after 4 days=14160+3560=17660 projects
Step 5: Calculate the work done by A alone on Day 5
On Day 5, A works alone:
Work done by A in 1 day=13=2060 projects
Now, adding this to the total work done:
Total work after 5 days=17660+2060=19660 projects
Step 6: Calculate the number of complete projects finished
To find out how many complete projects they finished, we divide the total work done by the work required for one project:
Number of projects completed=19660≈3.27
Since we can only count complete projects, they finished 3 complete projects.
Final Answer
Thus, the total number of projects they have finished in 5 days is 3.
---
- A can complete the project in 3 days, so A's work rate is:
Work rate of A=1 project3 days=13 projects per day
- B can complete the project in 4 days, so B's work rate is:
Work rate of B=1 project4 days=14 projects per day
- C can complete the project in 5 days, so C's work rate is:
Work rate of C=1 project5 days=15 projects per day
To find the total work rate when all three work together, we add their individual work rates:
Combined work rate=13+14+15
To add these fractions, we need a common denominator. The least common multiple (LCM) of 3, 4, and 5 is 60. Thus, we convert each fraction:
13=2060,14=1560,15=1260
Now we can add them:
Combined work rate=2060+1560+1260=4760 projects per day
In the first 3 days, all three work together:
Work done in 3 days=3×4760=14160 projects
After 3 days, C leaves. Now A and B continue working together for the next day (Day 4):
Work done by A and B in 1 day=13+14=2060+1560=3560 projects
So, after Day 4, the total work done is:
Total work after 4 days=14160+3560=17660 projects
On Day 5, A works alone:
Work done by A in 1 day=13=2060 projects
Now, adding this to the total work done:
Total work after 5 days=17660+2060=19660 projects
To find out how many complete projects they finished, we divide the total work done by the work required for one project:
Number of projects completed=19660≈3.27
Since we can only count complete projects, they finished 3 complete projects.
Thus, the total number of projects they have finished in 5 days is 3.
Topper's Solved these Questions
Similar Questions
PQRS is a square. SR is a tangent (at point S) to the circle with centre OandTR=OS. Then, the ratioof area of the circle to the area of the square is
View SolutionThe product of all integers from 1 to 100 will have the following number of zeros at the end:
(a)20
(b)21
(c)19
(d)24
View SolutionA, B और C किसी काम को क्रमश: 10 , 12 तथा 15 दिन में पूरा कर सकते है A ने काम पूरा होने से 5 दिन पहले काम छोड़ दिया और B ने A के काम छोड़ने के 2 दिन बाद काम छोड़ दिया । समस्त काम पूरा करने के लिए कितने दिनों की आवश्यकता होगी ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View Solution3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B and C start working together. After 2 days A left the work and after next 2 days C also left. Then find in how many days the whole work will be completed ?
View Solution21 typists can complete a project in 8 days. In how many days will 15 typists complete the project?
View SolutionA can do a piece of work in 25 days, B in 40 days and C in 60 days. All three worked for 5 days, after which A left. If B left 10 days before the completion of the work then in how many days the work was completed.
View Solutionदो शिक्षक A एवं B एक शैक्षिक कार्य को क्रमशः 10 दिनों एवं 15 दिनों में पूरा कर . सकते है। उन दोनों ने एक साथ कार्यारंभ किया, लेकिन A ने 5 दिन बाद कार्य छोड़ दिया एवं दूसरा शिक्षक C शामिल हो गया जो अकेले उस कार्य को 60 दिन में पूरा कर सकता है। वह काम कितने दिनों में समाप्त हुआ?
View Solution12 men can complete a project in 20 days. 18 women can complete that project in 16 days and 24 children can complete it in 18 days. 8 women and 16 children leave after working for 9 days. In how many days will 10 men complete the remaining work?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View Solution