15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .
The correct Answer is:16 days
To solve the problem step by step, we will first determine the total amount of work and then calculate how the work progresses over the days with the changes in the number of workers.
Step 1: Calculate the Total Work
Given that 15 men can complete the work in 12 days, we can calculate the total work in terms of "man-days".
Total work = Number of men × Number of days
Total work = 15 men × 12 days = 180 man-days
Step 2: Work Done in the First 4 Days
Next, we need to find out how much work is completed in the first 4 days by the 15 men.
Work done in 4 days = Number of men × Number of days
Work done in 4 days = 15 men × 4 days = 60 man-days
Step 3: Calculate Remaining Work
Now, we can find the remaining work after the first 4 days.
Remaining work = Total work - Work done in 4 days
Remaining work = 180 man-days - 60 man-days = 120 man-days
Step 4: Determine the New Number of Workers
After 4 days, 5 men leave the work, so the number of men left is:
Number of men left = 15 men - 5 men = 10 men
Step 5: Calculate Days Required to Finish Remaining Work
Now we need to find out how many days it will take for the remaining 10 men to finish the remaining work of 120 man-days.
Days required = Remaining work / Number of men
Days required = 120 man-days / 10 men = 12 days
Step 6: Calculate Total Days to Complete the Work
Finally, we add the 4 days worked initially to the 12 days required to finish the remaining work.
Total days = Days worked initially + Days required to finish remaining work
Total days = 4 days + 12 days = 16 days
Conclusion
The total work will be finished in 16 days.
---
Given that 15 men can complete the work in 12 days, we can calculate the total work in terms of "man-days".
Total work = 15 men × 12 days = 180 man-days
Next, we need to find out how much work is completed in the first 4 days by the 15 men.
Work done in 4 days = 15 men × 4 days = 60 man-days
Now, we can find the remaining work after the first 4 days.
Remaining work = 180 man-days - 60 man-days = 120 man-days
After 4 days, 5 men leave the work, so the number of men left is:
Now we need to find out how many days it will take for the remaining 10 men to finish the remaining work of 120 man-days.
Days required = 120 man-days / 10 men = 12 days
Finally, we add the 4 days worked initially to the 12 days required to finish the remaining work.
Total days = 4 days + 12 days = 16 days
The total work will be finished in 16 days.
Topper's Solved these Questions
Similar Questions
If man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View SolutionWhat value will come in place of question mark (?) in the questions given below?
123×14.5×114=?(3.4)2
View Solution16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work? 6 b. 12 c. 16 d. none of these
View Solution3 पुरुष किसी काम को 6 दिनों में समाप्त कर सकते है उनके काम शुरू करने के 2 दिनों के वे कितने दिनों में समाप्त करेंगे ?
View Solution16 महिलाएं किसी काम को 12 दिनों में पूरा कर सकती है जबकि उसी काम को 12 पुरुष 8 दिनों में पूरा कर सकते है 16 पुरुष काम करना शुरू करते है और 3 दिन के बाद 10 पुरुष काम छोड़ देते है उसकी जगह 4 महिलाएं आ जाती है तो शेष काम कितने दिनों में पूरा होगा ?
View Solution12 आदमी किसी कार्य को 90 दिनों में कर सकते है कार्य छोड़ प्रारभ होने के 30 दिनों के बाद 2 आदमियों ने कार्य को पूरा करने में कितने दिन लगेंगे ?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution25 men and 15 women can complete a work in 12 days. They all start working together and after working for 8 days the women stop working. Now 25 men can complete the remainder in 6 days. If only 15 women do the whole work, in how many days will that work be finished?
View SolutionIf 45 men can finish a piece of work in 12 days, in how many days will 30 men finish the same work?
View Solution15 men can complete a work in 24 days and 12 children in 60 days. 10 men started the work and after 12 days 12 children joined the work. In how many days will the remaining work be finished?
View Solution24 men can do a piece of work in 6 days and 10 men and 6 women together can do the same work in 12 days. Started the work with 3 men and after 16 days how many women join the work so that the remaining work can be finished in 8 days?
View SolutionIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
View Solution12 men can do a piece of work in 90 days. After 30 days from the start of the work 2 men left the work and 8 men joined. In how many days will it take to complete the remaining work?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?
View Solution