Four men and 6 women can complete a certain piece of work in 5 days whereas three men and 4 women can complete it in 7 days. How many men should assist 25 women to complete times the same work in 5 days?
10
4
8
5
The correct Answer is:D
To solve the problem step by step, we can follow these calculations:
Step 1: Define the Efficiency of Men and Women
Let the efficiency of one man be x and the efficiency of one woman be y.
Step 2: Set Up the Equations
From the problem statement, we have two scenarios:
1. Four men and six women can complete the work in 5 days:
Work=Efficiency×Time
5×(4x+6y)=Total Work(Equation 1)
2. Three men and four women can complete the work in 7 days:
7×(3x+4y)=Total Work(Equation 2)
Step 3: Equate the Total Work
Since both equations represent the same total work, we can set them equal to each other:
5(4x+6y)=7(3x+4y)
Step 4: Expand and Simplify
Expanding both sides gives:
20x+30y=21x+28y
Rearranging the equation:
20x−21x+30y−28y=0
−x+2y=0⇒x=2y
Step 5: Substitute to Find Total Work
Now, substitute x=2y back into one of the original equations to find the total work. Using Equation 1:
Total Work=5(4(2y)+6y)=5(8y+6y)=5(14y)=70y
Step 6: Determine the Work with 25 Women
Now we need to find how many men n are required to assist 25 women to complete 2.5 times the same work in 5 days:
Total Work for 2.5 times=2.5×70y=175y
Step 7: Set Up the New Equation
The equation for the work done by n men and 25 women in 5 days is:
5(n⋅x+25⋅y)=175y
Substituting x=2y:
5(n⋅2y+25y)=175y
5(2ny+25y)=175y
Dividing both sides by y (assuming y≠0):
5(2n+25)=175
Step 8: Solve for n
Dividing both sides by 5:
2n+25=35
Subtracting 25 from both sides:
2n=10
Dividing by 2:
n=5
Final Answer
The number of men required to assist 25 women to complete the work in 5 days is 5.
---
Let the efficiency of one man be x and the efficiency of one woman be y.
From the problem statement, we have two scenarios:
Work=Efficiency×Time
5×(4x+6y)=Total Work(Equation 1)
7×(3x+4y)=Total Work(Equation 2)
Since both equations represent the same total work, we can set them equal to each other:
5(4x+6y)=7(3x+4y)
Expanding both sides gives:
20x+30y=21x+28y
20x−21x+30y−28y=0
−x+2y=0⇒x=2y
Now, substitute x=2y back into one of the original equations to find the total work. Using Equation 1:
Total Work=5(4(2y)+6y)=5(8y+6y)=5(14y)=70y
Now we need to find how many men n are required to assist 25 women to complete 2.5 times the same work in 5 days:
Total Work for 2.5 times=2.5×70y=175y
The equation for the work done by n men and 25 women in 5 days is:
5(n⋅x+25⋅y)=175y
Substituting x=2y:
5(n⋅2y+25y)=175y
5(2ny+25y)=175y
Dividing both sides by y (assuming y≠0):
5(2n+25)=175
Dividing both sides by 5:
2n+25=35
Subtracting 25 from both sides:
2n=10
Dividing by 2:
n=5
The number of men required to assist 25 women to complete the work in 5 days is 5.
Similar Questions
4 men and 6 women can complete a certain work in 5 days, while 3 men and 4 women can do it in 7 days. How many men must help 25 women to complete 2-times of that work in 5 days?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?
View SolutionIn how manu days can the work be done by 9 men and 15 women ?
(i) 6 men and 5 women can complete the cork in 6 days.
(ii) 3 men and 4 women can complete the work in 10 days
(iii) 18 men and 15 women can complete the work in 2 days.
View Solution9 men and 12 women can complete a work in 4 days, whereas 3 men and 6 women can complete it in 10 days. The numberof days in which 15 women will complete the work is:
View SolutionIf 5 men can do a piece of work in 10 days and 12 women can do the same work in 15 days, then in how many days will 5 men and 6 women complete the same work?
View Solutionएक कार्य 12 व्यक्ति या 15 औरतें 20 दिन में पूरा करते हैं। वही कार्य 4 व्यक्ति तथा 5 औरतें कितने दिनों में पूरा करेंगे?
View Solution