A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
a)20
b)19
c)30
d)31
The correct Answer is:A
To solve the problem, we need to determine how many days C worked when A, B, and C worked together on a piece of work, with A leaving after 9 days and B leaving 3 days before the work was completed.
1. Determine the Work Rates of A, B, and C:
- A can complete the work in 24 days, so A's work rate is 124 of the work per day.
- B can complete the work in 36 days, so B's work rate is 136 of the work per day.
- C can complete the work in 108 days, so C's work rate is 1108 of the work per day.
2. Calculate the Total Work:
- The least common multiple (LCM) of 24, 36, and 108 is 216. Therefore, the total work can be considered as 216 units.
3. Calculate the Individual Work Rates in Units:
- A's work rate: 21624=9 units per day.
- B's work rate: 21636=6 units per day.
- C's work rate: 216108=2 units per day.
4. Calculate Work Done in the First 9 Days:
- In the first 9 days, A, B, and C work together:
- Total work done in 9 days = (9+6+2)×9=17×9=153 units.
5. Determine Remaining Work:
- Remaining work after 9 days = Total work - Work done in 9 days
- Remaining work = 216−153=63 units.
6. Calculate the Work Done by B and C:
- B leaves 3 days before the work is completed, meaning B works for T−3 days, where T is the total time taken to complete the work.
- Let x be the number of days B worked after A left. Hence, C worked for x+3 days.
7. Work Done by B and C Together:
- Work done by B and C in the remaining days = (6+2)×x=8x.
- Since they need to complete the remaining 63 units, we have:
- 8x=63
- x=638=7.875 days.
8. Total Days Worked:
- Total days worked by C = Days worked together + Days worked after A left
- C worked for 9 days (with A and B) + 7.875 days (with B) = 9+7.875=16.875 days.
9. Final Calculation:
- Since B left 3 days before the work was completed, C worked for an additional 3 days alone to finish the work.
- Therefore, total days C worked = 16.875+3=19.875 days.
Conclusion:
C worked for approximately 20 days.
- A can complete the work in 24 days, so A's work rate is 124 of the work per day.
- B can complete the work in 36 days, so B's work rate is 136 of the work per day.
- C can complete the work in 108 days, so C's work rate is 1108 of the work per day.
- The least common multiple (LCM) of 24, 36, and 108 is 216. Therefore, the total work can be considered as 216 units.
- A's work rate: 21624=9 units per day.
- B's work rate: 21636=6 units per day.
- C's work rate: 216108=2 units per day.
- In the first 9 days, A, B, and C work together:
- Total work done in 9 days = (9+6+2)×9=17×9=153 units.
- Remaining work after 9 days = Total work - Work done in 9 days
- Remaining work = 216−153=63 units.
- B leaves 3 days before the work is completed, meaning B works for T−3 days, where T is the total time taken to complete the work.
- Let x be the number of days B worked after A left. Hence, C worked for x+3 days.
- Work done by B and C in the remaining days = (6+2)×x=8x.
- Since they need to complete the remaining 63 units, we have:
- 8x=63
- x=638=7.875 days.
- Total days worked by C = Days worked together + Days worked after A left
- C worked for 9 days (with A and B) + 7.875 days (with B) = 9+7.875=16.875 days.
- Since B left 3 days before the work was completed, C worked for an additional 3 days alone to finish the work.
- Therefore, total days C worked = 16.875+3=19.875 days.
C worked for approximately 20 days.
समान प्रश्न
A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
ज्ञान जांच
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of theseA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
View SolutionA, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View SolutionA and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View Solution