40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in

A

A. 5623 days

B

B. 5313 days

C

C. 52 days

D

D. 50 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A


माना 1 व्यक्ति द्वारा 1 दिन किया गया कार्य = 1 इकाई
कुल कार्य =40×40=1600 unit
40 व्यक्तियों द्वारा 10 दिन में किया गया कार्य = 400 unit.
A/Q
35 men 10 दिनों में = 350 unit.
30 men 10 दिनों में = 300 unit
25 men 10 दिनों में = 250 unit
20 men 10 दिनों में = 200 unit
बाकी व्यक्ति = 20-5 =15
तथा बाकी काम = 1600-1500 = 100 unit
बाकी काम को खत्म करने में लगा समय 10015=623day लगा समय 10015=623day
कुल दिन =50+623=5623 day

|


Similar Questions


Knowledge Check

  • 40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in

    AA. 5623 days
    BB. 5313 days
    CC. 52 days
    DD. 50 days
  • 60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

    A36
    B30
    C40
    D45
  • 50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

    A60
    B30
    C40
    D50